Madera Health/Fitness
Project Status
Madera Center Health Fitness
Measure E Budget: $299,000
Total Expenses to Date: $222,204
Balance: $76,796
Construction is complete and the project was accepted at the July 2007 Board meeting. Final invoices are being received and processed, with the expectation that the final balance of the project will be reduced to zero.
The Physical Education room is complete. Construction is in progress for the Fitness Center.
Project was awarded by the Board at the December 2006 Board meeting.