Willow International Phase I - Food Service/Bookstore
Project Status
Willow International Phase I – Foodservice / Bookstore
Measure E Budget: $2,814,258
Total Expenses to Date: $2,616,303
Balance: $197,955
Construction is complete and both phases of the project were accepted at the April Board meeting. This project will no longer be detailed in future reports.
Willow International Phase I – Foodservice / Bookstore
Measure E Budget: $2,814,258
Total Expenses to Date: $211,249
Balance: $2,603,009
The project has been bid and awarded at the May 2007 Board meeting. Site work is in progress in preparation for the delivery of the portable units September 2007.