Health/Fitness Center
Project Status
FCC Health Fitness Center (Physical Performance Center)
Measure E Budget: $1,699,576
Total Expenses to Date: $1,457,010
Balance: $242,566
Construction is complete and was accepted at the July 2007 Board meeting. Final invoices are being received and processed, with the expectation that the final balance of the project will be reduced to zero.
Construction is in progress.
Construction is in progress.
Project Title: FCC Health / Fitness Center
Funding Source: Measure E
Project Description: The project will construct new facilities on the east side of campus (east side of Blackstone Blvd.). The facility will include classrooms, offices, and labs for the FCC physical education and athletics programs.
Anticipated Completion Date: Fall/Winter 2007
Status: Project was awarded at the May 2, 2006 Board Meeting and construction began June 2006.
Estimated Project Budget: Prepared by Kitchell - Program Manager
Funding Source: Measure E
Estimated Project Budget |
2002-05 |
2005-06 |
2005-06 |
2005-06 |
Total Expenditures |
|
Design Services |
118,699 |
21,433 |
47,168 |
43,168 |
4,000 |
64,601 |
Consultant Services |
39,080 |
1,461 |
5,000 |
4,681 |
319 |
6,142 |
Fees & Other Charges |
31,297 |
2,800 |
12,000 |
10,255 |
0 |
13,055 |
Construction & Equipment |
1,329,000 |
0 |
21,000 |
0 |
0 |
0 |
Inspection & Testing |
116,500 |
3,200 |
7,500 |
3,750 |
0 |
6,950 |
Contingency |
65,000 |
0 |
0 |
0 |
0 |
0 |
Total |
1,699,576 |
28,894 |
92,668 |
61,854 |
4,319 |
90,748 |
Project Title: FCC Health / Fitness Center
Funding Source: Measure E
Project Description: The project will construct new facilities on the east side of campus (east side of Blackstone Blvd.). The facility will include classrooms, offices, and labs for the FCC physical education and athletics programs.
Anticipated Completion Date: Fall/Winter 2007
Status: Project bids April 2006 and will be taken to the Board for award May 2006.
Estimated Project Budget: Prepared by Kitchell - Program Manager
Funding Source: Measure E
Estimated Project Budget |
2002-05 |
2005-06 |
2005-06 |
2005-06 |
Total Expenditures |
|
Design Services |
91,478 |
21,433 |
55,107 |
36,371 |
4,000 |
57,804 |
Consultant Services |
26,769 |
1,461 |
8,000 |
1,295 |
400 |
2,756 |
Fees & Other Charges |
15,999 |
2,800 |
12,000 |
8,549 |
0 |
11,349 |
Construction & Equipment |
1,336,240 |
0 |
21,000 |
0 |
0 |
0 |
Inspection & Testing |
92,923 |
3,200 |
5,000 |
0 |
0 |
3,200 |
Contingency |
44,615 |
0 |
0 |
0 |
0 |
0 |
Total |
1,608,024 |
28,894 |
101,107 |
46,215 |
4,400 |
75,109 |
Funding Source: Measure E
Project Description: The project will construct new facilities on the east side of campus (east side of Blackstone Blvd.). The facility will include classrooms, offices, and labs for the FCC physical education and athletics programs.
Anticipated Completion Date: Fall/Winter 2007
Status: BCA Architects has conducting preliminary meetings with District to develop schematic design. BCA submitted schematic design to Office of State Architect for preliminary review and comments regarding access compliance. BCA currently proceeding with Working Drawings.
Estimated Project Budget: Prepared by Kitchell - Program Manager
Funding Source: Measure E
Estimated Project Budget |
2002-05 |
2005-06 |
2005-06 |
2005-06 |
Total Expenditures |
|
Design Services |
71,385 |
17,607 |
|
16,170 |
38,936 |
33,777 |
Consultant Services |
26,769 |
1,461 |
8,000 |
367 |
6,838 |
1,828 |
Fees & Other Charges |
15,999 |
2,800 |
8,000 |
6,164 |
0 |
8,964 |
Construction & Equipment |
1,356,333 |
0 |
21,000 |
0 |
0 |
0 |
Inspection & Testing |
92,923 |
2,059 |
5,000 |
0 |
0 |
2,059 |
Contingency |
44,615 |
0 |
0 |
0 |
0 |
0 |
Total |
1,608,024 |
23,927 |
42,000 |
22,701 |
45,774 |
46,628 |
Funding Source: Measure E
Project Description: The project will construct new facilities on the east side of campus (east side of Blackstone Blvd.).The facility will include classrooms, offices, and labs for the FCC physical education and athletics programs.
Anticipated Completion Date: 2007
Status: BCA Architects has conducting preliminary meetings with District to develop schematic design.BCA submitted schematic design to Office of State Architect for preliminary review and comments regarding access compliance. BCA currently proceeding with Working Drawings.
Estimated Project Budget: Prepared by Kitchell - Program Manager
Funding Source: Measure E
Estimated Project Budget |
2002-05 |
2005-06 |
2005-06 |
2005-06 |
Total Expenditures |
|
Design Services |
71,385 |
17,607 |
30,000 |
0 |
0 |
17,607 |
Consultant Services |
26,769 |
1,461 |
5,000 |
0 |
0 |
1,461 |
Fees & Other Charges |
15,999 |
2,800 |
0 |
0 |
0 |
2,800 |
Construction & Equipment |
892,308 |
0 |
21,000 |
0 |
0 |
0 |
Inspection & Testing |
92,923 |
2,059 |
5,000 |
0 |
0 |
2,059 |
Contingency |
44,615 |
0 |
0 |
0 |
0 |
0 |
Total |
1,143,999 |
23,927 |
61,000 |
0 |
0 |
23,927 |
BCA Architects has conducting preliminary meetings with District to develop schematic design. BCA will submit schematic design to Office of State Architect for preliminary review and comments regarding access compliance by May 2005. BCA and the District will then proceed with programming and design development.
Architect approval by Board is scheduled for January 11, 2005. Programming and schematic design will begin Spring semester of 2005.