LAN/WAN Phase III
Project Status
Completed on Schedule
(will not be shown on future Bond Oversight Committee Status Reports)
Funding Source: Measure E
Project Description: This project has been phased over several years with the first two phases having been completed prior to the passage of Measure E. This project improved the District’s Wide Area and Local Area network infrastructure to support instructional, administrative, and student service activities. Phase III included the extension of the existing site pathway foundation previously installed under earlier phases at Fresno City College; complete renovation of the Math/Science and Library buildings telecommunications infrastructure, horizontal pathways, and network electronics at Fresno City College; as well as new network electronics for designated buildings at Fresno City College. Phase III has been completed and was accepted at the January 13, 2004 Board meeting.
Status: Completed on Schedule
Estimated Project Budget: Actuals
Estimated Project Budget | 2002-04 Actual Expenditures | Total Actual Expenditures | |
---|---|---|---|
Design Services | 124,000 | 128,105 | 128,105 |
Consultant Services | 0 | 0 | 0 |
Fees & Other Charges | 3,000 | 2,955 | 2,955 |
Construction / Contingency | 1,833,000 | 1,920,163 | 1,920,163 |
Inspection & Testing | 40,000 | 41,871 | 41,871 |
Total | 2,000,000 | 2,093,094 | 2,093,094 |
Completed
This project had been phased over several years with the first two phases having been completed prior to the passage of Measure E. Phase III is complete and was accepted at the January 13 Board meeting.
This project has been phased over several years with the first two phases having been completed prior to the passage of Measure E. The current phase is Phase III and has been completed and accepted by the district.
This project has been phased over several years with the first two phases having been completed prior to the passage of Measure E. The current phase is Phase 3 and is scheduled for completion this fall. The SCCCD Board of Trustees at its April 1 meeting selected and authorized the administration to enter into an agreement with HCI, Inc., as the project engineer for the next phase(s) of the project. The District has held initial planning and design development meetings with the engineer to develop the parameters of the project phase(s).